Execution of a complex of construction and installation works at a confectionery factory

Customer – OOO “Ingredie”

  • Contract for the general contract for the modernization of the production facilities of the confectionery factory
    Ingredika was signed in March 2020. The deadline is June 2020.
  • The construction area is 2500 m2. The metal capacity of the object is 70 tons. The volume of monolithic works is 200 m3.
  • The work is complicated by the access regime due to the pandemic.
  • Currently engaged at the facility:
    special equipment 1 unit;
    1 engineer;
    Construction workers – 12 people.
  • Types of work performed:
    dismantling works – set
    construction of engineering networks – water supply, drainage, ventilation, heating
    monolithic works – 150 m3
    installation of sandwich – 1700 m2
    installation of metal structures – 27 t.

Status – the object is passed.