Construction of a data processing center, Delta building

slide-1

Client: Data-center-delta

Place of construction – Vladimir. The work starts in October 2022.

Works performed:

  • Clearing the land
  • Preparation of the site for construction
  • Summing up of main engineering communications
  • Construction of temporary roads
  • Earthworks
  • Arrangement of the pile field
  • Construction of foundations
  • Overlap device
  • Installation of rough floors
  • Installation of columns
  • Installation of metal structures (trusses, beams, half-timbered frames, etc.)
  • Staircases and marches
  • Installation of the railway plinth
  • Installation of facade sandwich panels
  • Installation of the roof Installation of stained glass windows, doors, windows
  • Installation of gates, bridges, curtains, hermetization
  • The device of reinforced floors with preparation
  • Finishing works
  • Internal engineering
  • Installation of equipment
  • Kit VK, OViK, AUPT, APS, SOWE, EO, EM, ES